Freeman Hall Road Bridge over North River

Nottingham, New Hampshire

 

The commencement of the Freeman Hall Road Bridge replacement was initiated in May of 2006 when the existing culvert collapsed due to the structural deficiency and poor roadway alignment.

 

Services Provided:

bullet

Engineering study (Survey, Borings, Etc.)

bullet

Hydraulic analysis

bullet

Bridge design

bullet

Permit Applications

bullet

Bidding Administration

bullet

Construction Contract Administration

bullet

Construction Observation/Engineering

 

Goals:

bullet

Improve roadway alignment

bullet

Increase hydraulic capacity

 

Project Highlights:

bullet

NHDOT Municipal Bridge Aid Program Project

bullet

14’-0” X 11’-0” Rise precast concrete box culvert with architectural form liner

bullet

Construction completed in approximately six weeks

bullet

Low bid: $347,000 (Busby Construction 06-26-06) Engineering Estimate: $381,000

 